Paving repairs, seal coating and installation of speed bumps will begin on Monday, August 17, 2009. The initial repairs to the broken asphalt will be first, followed by seal coating. All cars will need to be removed from the parking areas to the east of River Isle or they will be towed! The streets that will be worked on are: River Isle, Harbor Mist, River Town, Island, Mist, Mist River, and the alley ways behind homes. Island Place is a city street and not ours to repair.
The plan is to start sealing that area first to allow for parking as the other areas are done. The entire process, weather and resident cooperation permitting, should take not more than one week.
Flyers and leaflets will be distributed on Sunday by the paving company. Areas that will be in work or planned to be in work will be roped off.
Thank you!